1. With reference to Public-Private Partnership (PPP) models in infrastructure, consider the following statements: 1. In the Build-Operate-Transfer (BOT) model, the private entity operates the asset during the operational phase but does not own it. 2. The government bears no financial risk in the BOT model. 3. The BOT model is commonly used in road and highway projects. Which of the statements given above is/are correct?

  1. (a) 1 and 2 only
  2. (b) 1 and 3 only
  3. (c) 2 and 3 only
  4. (d) 1, 2 and 3

Answer: (b) 1 and 3 only

In the BOT model, the private entity builds and operates the asset under a concession agreement, but typically does not own it during the operational phase; ownership usually remains with the government or transfers back at the end of the concession period. The private entity bears the majority of financial and operational risk, but the government may still bear some residual financial risks (e.g., political risk, minimum revenue guarantees in some cases). BOT is commonly used in road and highway projects. Therefore, statements 1 and 3 are correct, while statement 2 is incorrect.

2. Consider the following statements regarding BharatNet: 1. It is a project to provide high-speed internet connectivity to all gram panchayats. 2. It is implemented by the Department of Telecommunications. 3. It is a part of the Digital India programme. Which of the statements given above is/are correct?

  1. (a) 1 and 2 only
  2. (b) 1 and 3 only
  3. (c) 2 and 3 only
  4. (d) 1, 2 and 3

Answer: (d) 1, 2 and 3

BharatNet is a flagship project under the Digital India programme, so Statement 3 is correct. It aims to provide high-speed broadband connectivity to all gram panchayats, so Statement 1 is correct. The project is administered by the Department of Telecommunications (DoT) and executed through Bharat Broadband Network Limited (BBNL), a Special Purpose Vehicle set up under DoT. Since DoT is the implementing ministry that drives the project through BBNL, Statement 2 is treated as correct. All three statements are correct, so the answer is (d).

3. Which of the following statements about the National Investment and Infrastructure Fund (NIP) is/are correct? 1. It is a sovereign fund established to attract foreign direct investment (FDI) in infrastructure. 2. It invests in both greenfield and brownfield infrastructure projects. 3. It operates under the administrative control of the Ministry of Finance.

  1. (a) 1 and 2 only
  2. (b) 2 and 3 only
  3. (c) 1 only
  4. (d) 1, 2 and 3

Answer: (b) 2 and 3 only

The fund in question is the National Investment and Infrastructure Fund (NIIF), not 'NIP'. NIIF is a quasi-sovereign fund set up to mobilise long-term domestic and foreign capital for infrastructure. It invests in both greenfield and brownfield projects (statement 2 correct) and the government holds a stake in it, with the Ministry of Finance overseeing it (statement 3 correct). Statement 1 is misleading: NIIF's core purpose is to catalyse and co-invest private capital, not merely to attract FDI. Hence only statements 2 and 3 are correct.

4. With reference to the 'Green Energy Corridors' project, consider the following statements: 1. It is aimed at integrating renewable energy into the national grid. 2. It is being implemented by the Ministry of New and Renewable Energy (MNRE). 3. It includes the development of dedicated transmission lines for renewable power. Which of the statements given above is/are correct?

  1. (a) 1 and 2 only
  2. (b) 1 and 3 only
  3. (c) 2 and 3 only
  4. (d) 1, 2 and 3

Answer: (d) 1, 2 and 3

All three statements are correct. Statement 1 is correct as the Green Energy Corridors project aims to integrate large-scale renewable energy into the national grid. Statement 2 is correct because the project is a scheme of the Ministry of New and Renewable Energy (MNRE), implemented on the ground by Power Grid Corporation of India (inter-state lines) and state transmission utilities (intra-state lines). Statement 3 is correct as the project involves building dedicated transmission lines to evacuate renewable power.

5. With respect to the National Infrastructure Pipeline (NIP), consider the following statements: 1. The NIP includes projects with a timeline extending beyond 2025. 2. It is a static database that does not allow dynamic updates. 3. The NIP ensures that infrastructure projects are evaluated for environmental and social impact before approval. Which of the statements given above is/are correct?

  1. (a) 1 and 3 only
  2. (b) 2 and 3 only
  3. (c) 1 only
  4. (d) 1, 2 and 3

Answer: (c) 1 only

Statement 2 is incorrect: the NIP is a dynamic, regularly updated database, not a static one. Statement 3 is incorrect: the NIP is an investment pipeline/database for project funding and monitoring; it does NOT itself mandate or build in environmental and social impact assessment as a pre-approval screening step. Environmental/social clearances are handled under separate environmental and forest laws, not by the NIP framework. Therefore only statement 1 is correct.

6. Consider the following statements regarding BharatNet: 1. It is a project to provide high-speed internet connectivity to all gram panchayats. 2. It is implemented by the Department of Telecommunications. 3. It is a public-private partnership model. Which of the statements given above is/are correct?

  1. (a) 1 only
  2. (b) 1 and 2 only
  3. (c) 2 and 3 only
  4. (d) 1, 2 and 3

Answer: (d) 1, 2 and 3

BharatNet aims to provide high-speed broadband connectivity to all gram panchayats (Statement 1 correct). It is implemented under the Department of Telecommunications (DoT) through Bharat Broadband Network Limited and the Universal Service Obligation Fund (Statement 2 correct). Statement 3 is incorrect because BharatNet is a government-led, USOF-funded initiative and is not structured as a public-private partnership model. Hence only statements 1 and 2 are correct.

7. Consider the following: The government recently announced that large hydro projects will be given 'renewable energy' status for the purpose of certain benefits. Which of the following statements is correct in this context?

  1. (a) Large hydro projects are now fully classified as renewable energy under MNRE.
  2. (b) Large hydro projects are now eligible for Renewable Purchase Obligation (RPO) but still not counted in the 500 GW target.
  3. (c) Large hydro projects are now eligible for certain benefits like tariff rationalization but are not classified as RE for RPO.
  4. (d) Large hydro projects are now treated as renewable energy for all purposes including RPO and national targets.

Answer: (d) Large hydro projects are now treated as renewable energy for all purposes including RPO and national targets.

Following the 2019 policy change, large hydropower projects (above 25 MW) were accorded 'renewable energy' status for ALL purposes — including eligibility for Renewable Purchase Obligation (RPO) compliance (as Hydropower Purchase Obligation/HPO) and being counted towards India's 500 GW non-fossil fuel target by 2030. Option (d) correctly captures this comprehensive treatment. Option (c) is factually wrong in stating large hydro is 'not classified as RE for RPO'

8. Consider the following statements about the Credit Linked Subsidy Scheme (CLSS) under PMAY: 1. It provides interest subsidy on home loans for EWS, LIG, and MIG categories. 2. The subsidy is available only for new houses, not for renovation. 3. The subsidy amount is credited upfront to the loan account. Which of the above statements is/are correct?

  1. (a) 1 and 3 only
  2. (b) 1 and 2 only
  3. (c) 2 and 3 only
  4. (d) 1, 2 and 3

Answer: (a) 1 and 3 only

Statement 1 is correct: CLSS provides interest subsidies on home loans for EWS, LIG, and MIG categories. Statement 2 is incorrect: CLSS under EWS and LIG also covers incremental housing (renovation and extension of existing pucca house), not only new construction. Statement 3 is correct: the subsidy is calculated as net present value and credited upfront to the borrower's loan account, reducing the outstanding principal. The correct combination is 1 and 3 only

9. Consider the following statements about hydro power in India: 1. Small hydro projects (up to 25 MW) are eligible for Renewable Purchase Obligation (RPO) compliance. 2. Large hydro projects are included in the national renewable energy target of 500 GW by 2030. Which of the statements given above is/are correct?

  1. (a) 1 only
  2. (b) 2 only
  3. (c) Both 1 and 2
  4. (d) Neither 1 nor 2

Answer: (c) Both 1 and 2

Statement 1 is correct: small hydro projects (up to 25 MW) are classified as renewable energy and are eligible for Renewable Purchase Obligation (RPO) compliance. Statement 2 is also correct: following the 2019 amendment to the Electricity Act, large hydro projects were given renewable energy status and are counted towards India's 500 GW non-fossil fuel target by 2030. Both statements are correct, making option (c) — 'Both 1 and 2' — the right answer.

10. Which of the following is a key regulatory mechanism that facilitates inter-state transmission of renewable energy and is closely linked to the Green Energy Corridor?

  1. (a) Renewable Energy Certificate (REC) mechanism
  2. (b) Inter-State Transmission System (ISTS) charges waiver for solar and wind
  3. (c) National Solar Mission
  4. (d) Perform, Achieve and Trade (PAT) scheme

Answer: (b) Inter-State Transmission System (ISTS) charges waiver for solar and wind

To promote RE, the government waived Inter-State Transmission System (ISTS) charges for solar and wind projects (initially for 25 years, later extended). This makes it cheaper to transmit RE from generation states to other states. The Green Energy Corridor provides the physical infrastructure, while the ISTS waiver provides the financial incentive. RECs (a) are for trading renewable energy attributes, but the waiver directly reduces transmission cost.

11. Which of the following is a major challenge in the implementation of PPP projects in India?

  1. (a) Excessive private sector involvement in policy formulation
  2. (b) Lack of long-term financing options
  3. (c) Over-reliance on government guarantees
  4. (d) High level of public sector ownership in all projects

Answer: (b) Lack of long-term financing options

A major, well-documented challenge for PPP projects in India is the lack of long-term financing. Infrastructure needs patient, long-tenure funds, but Indian banks face asset-liability mismatch and the corporate bond market is shallow, so adequate long-term finance is hard to mobilise (a problem the Kelkar Committee on PPPs flagged). option (c) is not the core challenge; option (d) is false as PPPs rely on private operators, not high public ownership.

12. Consider the following statements regarding PM Gati Shakti: 1. It is a digital platform for integrated infrastructure planning. 2. It aims to reduce project implementation time by eliminating inter-departmental delays. 3. It is managed by the Ministry of Electronics and Information Technology. Which of the statements given above is/are correct?

  1. (a) 1 and 2 only
  2. (b) 2 and 3 only
  3. (c) 1 only
  4. (d) 1, 2 and 3

Answer: (a) 1 and 2 only

PM Gati Shakti is a digital platform launched by the Government of India to integrate infrastructure planning across ministries and states. It aims to reduce delays by enabling coordinated planning and avoiding duplication. However, it is managed by the Department for Promotion of Industry and Internal Trade (DPIIT), Ministry of Commerce and Industry, not the Ministry of Electronics and Information Technology. Statements 1 and 2 are correct

More Indian Economy topics

This page shows 12 of 494 questions on this topic. The full set, with progress tracking and five agent perspectives per question, is in the JupiteX app — browse the exam catalogue or browse the Learn library.