How India’s delay is set to leave Rs135m of Nepal’s electricity unsold daily
Nepal cannot currently sell some of its surplus electricity abroad because its approval to export 609MW to Indian states expired at the end of October. The separate seasonal arrangement to supply 40MW to Bangladesh also ended. Without renewed arrangements, this electricity has no current export route under those deals. The Nepal Electricity Authority (NEA) usually seeks to move power covered by expiring medium-term agreements to India’s exchange. It submitted a request in August to convert the arrangements into exchange-based exports, but the Indian side had not approved it nearly three months later. Exchange sales let Nepal sell power when domestic generation exceeds demand. The delay comes as Nepal is generating 2,600MW to 2,700MW, while domestic demand is around 2,200MW to 2,300MW. Some power must stay in reserve, but the remaining surplus is difficult to sell abroad. The NEA estimates the halted exports put Rs135.82 million in potential daily revenue at risk.
Why is Nepal unable to sell some of its surplus electricity abroad right now?
Nepal cannot currently sell some of its surplus electricity abroad because its approval to export 609MW to Indian states expired at the end of October. The separate seasonal arrangement to supply 40MW to Bangladesh also ended. Without renewed arrangements, this electricity has no current export route under those deals.
The Nepal Electricity Authority (NEA) usually seeks to move power covered by expiring medium-term agreements to India’s exchange. It submitted a request in August to convert the arrangements into exchange-based exports, but the Indian side had not approved it nearly three months later. Exchange sales let Nepal sell power when domestic generation exceeds demand.
The delay comes as Nepal is generating 2,600MW to 2,700MW, while domestic demand is around 2,200MW to 2,300MW. Some power must stay in reserve, but the remaining surplus is difficult to sell abroad. The NEA estimates the halted exports put Rs135.82 million in potential daily revenue at risk.
How much electricity is affected, and how much potential revenue could Nepal lose each day?
The export interruption affects 649MW in total. That is power Nepal had been supplying through arrangements with India and Bangladesh, but which it cannot currently sell through those routes. The lost opportunity matters because the NEA earns revenue by selling surplus electricity abroad.
The larger portion is 609MW supplied to three Indian states: 404MW to Haryana and 205MW to Uttar Pradesh and Bihar. Another 40MW went to Bangladesh under a seasonal arrangement that ran annually from June 15 to November 15. The Indian approvals expired at October’s end, and the Bangladesh export period also ended.
The NEA estimates that the paused exports represent Rs135.82 million in potential daily revenue, equivalent to about INR84.88 million. The estimate uses an average export rate of 5.45 Indian rupees per unit. This is potential revenue, not a stated final loss; the amount at risk depends on the electricity remaining unsold.
How could Nepal go from having unsold surplus electricity now to needing to import power in winter?
Nepal’s electricity balance changes with the seasons. During the monsoon, rivers carry more water, allowing hydropower plants to generate more electricity. If generation exceeds domestic demand, the NEA has surplus power that it can sell abroad. Right now, however, some export arrangements have expired, limiting its ability to sell that extra electricity.
The article gives a current example: Nepal is generating between 2,600MW and 2,700MW against demand of around 2,200MW to 2,300MW. But river flows begin to decline from November-end, so hydropower output and exportable volumes fall. The NEA also keeps 200MW to 300MW in reserve for system security, rather than treating every generated unit as available for export.
By winter, domestic generation is expected to fall below demand. The NEA estimates it will need to import around 500MW continuously from mid-January to mid-March. During peak-demand hours, imports could rise to 800MW to 900MW. So the current surplus does not mean Nepal will have excess power year-round.
Who approves Nepal’s access to India’s electricity exchange, and what role does Nepal Electricity Authority play?
India’s approval is needed for Nepal to sell the electricity through the Indian Energy Exchange (IEX). The article refers to approval from the “Indian side” but does not identify a specific ministry, regulator, or other agency. That distinction matters: the NEA can request the change, but it cannot authorise access on India’s behalf.
The Nepal Electricity Authority is the state-owned power utility and Nepal’s exporter in these arrangements. It supplies electricity to Indian states under medium-term bilateral agreements and also sells surplus power through the IEX’s day-ahead and real-time markets. In August, NEA Managing Director Dirghayu Kumar Shrestha said the utility had asked to convert the existing arrangements into exchange-based exports.
The request had still not received approval nearly three months later, while the 609MW Indian export authorisation expired at October’s end. The article also describes a request to convert 649MW covered by medium-term arrangements. Until the Indian side approves the switch, the NEA cannot use the exchange to sell that contracted electricity.
What is an electricity exchange, and how is selling power there different from a bilateral agreement?
An electricity exchange is a marketplace for trading electricity. In this case, Nepal uses India’s Indian Energy Exchange (IEX), including its day-ahead and real-time markets. The article says prices in those markets are determined competitively. In general, exchange trading lets sellers offer power into a market where buyers can purchase it, rather than arranging each sale directly with a particular buyer.
A bilateral agreement is a direct arrangement between parties. Nepal’s medium-term agreements supply set amounts to Indian states, including Haryana, Bihar, and Uttar Pradesh. For example, Nepal has supplied 404MW to Haryana and another 205MW to Uttar Pradesh and Bihar. Those arrangements are different from selling surplus power through the IEX.
The NEA usually seeks to convert expiring bilateral arrangements into exchange-based exports. This could let Nepal sell more power when domestic generation exceeds demand, but it needs Indian approval to make the switch. The current delay means expired agreements cannot simply be replaced with exchange sales, even though the exchange is where Nepal has traditionally sold monsoon surplus.
Why does Nepal usually have more hydropower to export during the monsoon than in winter?
Nepal relies on hydropower, so the amount of electricity available changes with river flows. In the monsoon, rivers carry greater volumes of water, and hydropower generation and export volumes are typically higher. When output exceeds domestic demand, the extra electricity can be sold abroad if export approvals and arrangements are in place.
The article describes a current surplus: Nepal is generating 2,600MW to 2,700MW, while domestic demand is around 2,200MW to 2,300MW. That gap helps explain why the NEA has been seeking export routes. It cannot export all the surplus, though; it must keep 200MW to 300MW in reserve to protect system security and domestic supply.
The seasonal shift reverses as river flows begin to decline from November-end. Hydropower generation and the amount available for export then fall. By winter, the NEA expects domestic generation to be below demand and plans to import power from India. Its estimate is around 500MW continuously from mid-January to mid-March, with higher imports during peak hours.
Why must an electricity system keep spare generating capacity in reserve instead of exporting every available unit?
Electricity systems need a buffer so supply can keep serving users if generation unexpectedly drops. As a general grid principle, demand and supply must remain balanced; keeping spare capacity available helps the system respond when a plant trips offline. Exporting every available unit would leave less room to handle such a disruption.
The NEA says it needs to retain around 200MW to 300MW for system security and to prevent disruptions to domestic supply if a major power plant suddenly goes offline. The article gives the 456MW Upper Tamakoshi Hydropower Project as an example of a large facility whose unexpected outage could require that reserve.
That means Nepal’s exportable surplus is smaller than the difference between total generation and domestic demand. The NEA currently reports generation of 2,600MW to 2,700MW against demand of 2,200MW to 2,300MW, but it cannot treat all of that gap as available for sale. Reserves protect domestic reliability even while export approvals are delayed.
This brief was written by AI from the original reporting and checked by other models. Names, figures and quotes come from the source; read it for full context.