Economy & Business23 Nov 2026 · about 7 min

Flagship UK gigafactory plan in turmoil after it loses second builder in five months

The brief

TSL, the construction specialist contracted by Agratas, is leaving the Somerset battery factory project after the two companies failed to agree terms. Sources told the Guardian that disagreements over the project’s timeline and cost were at the heart of the dispute. TSL is formally known as Tonroe Group. It is the second main contractor to depart in five months. Agratas fired its predecessor, Sir Robert McAlpine (SRM), at short notice in June. One source suggested that discussions about the terms of SRM’s departure are still ongoing. The disputes with TSL are described as similar to those involving SRM. TSL is expected to leave the site within two or three months. No other main build contractor is lined up, although NG Bailey, currently handling mechanical, electrical and plumbing work, could be an option to take over the whole build. The departures add uncertainty to the project’s schedule, but Agratas says it is on track to meet customer requirements.

01

Why is TSL leaving the project, and which contractor left before it?

TSL, the construction specialist contracted by Agratas, is leaving the Somerset battery factory project after the two companies failed to agree terms. Sources told the Guardian that disagreements over the project’s timeline and cost were at the heart of the dispute. TSL is formally known as Tonroe Group.

It is the second main contractor to depart in five months. Agratas fired its predecessor, Sir Robert McAlpine (SRM), at short notice in June. One source suggested that discussions about the terms of SRM’s departure are still ongoing. The disputes with TSL are described as similar to those involving SRM.

TSL is expected to leave the site within two or three months. No other main build contractor is lined up, although NG Bailey, currently handling mechanical, electrical and plumbing work, could be an option to take over the whole build. The departures add uncertainty to the project’s schedule, but Agratas says it is on track to meet customer requirements.

02

What is a gigafactory, and what does it make?

A gigafactory is a very large industrial facility that manufactures batteries at scale. The term describes the scale of battery production, rather than a different kind of battery. In general, these factories turn battery materials and components into finished battery cells or packs for uses such as electric vehicles.

The Somerset project is being built by Agratas, a Tata Group company, to provide batteries for its sister company, Jaguar Land Rover (JLR). The planned factory is in Bridgwater and is expected to employ as many as 4,200 people. The article describes batteries as important parts of electric vehicles, but does not give the factory’s planned output capacity.

The project matters because battery supply is dominated globally by China, South Korea and Japan. The UK government has pledged £380m in support, seeing the factory as important to the long-term survival of the British car industry. The build has faced contractor changes and delays, however, and Agratas’s latest target is to start production in January 2028.

03

How large is the Somerset project in cost, government support and planned workforce?

Agratas’s planned battery factory in Bridgwater, Somerset, is valued at £5.2bn. It is intended to supply batteries to Jaguar Land Rover, Agratas’s sister company within Tata Group. The project is presented as a major industrial investment, not simply a construction site: the government considers it important to the long-term survival of Britain’s car industry.

The UK government has pledged £380m in financial support, although not all of that subsidy has been paid out. When Tata announced the project in 2023, it aimed to start production in 2026 and employ as many as 4,200 people. The production goal was later pushed back to 2027, and the latest target mentioned is January 2028.

The site’s building shell is mostly complete, and National Grid has begun work on the electricity substation needed to supply the factory. But contractor departures have raised doubts about the schedule. TSL is leaving after disputes over time and cost, and no replacement main build contractor is lined up, though NG Bailey could be an option.

04

What does losing its main contractor put at risk, and what is the factory’s latest planned start date?

Losing TSL puts the construction schedule and the factory’s latest production target under pressure. TSL is the second main contractor to leave in five months, following Sir Robert McAlpine, which Agratas fired in June. Sources said the disputes involved project timing and cost, and the two contractor departures have raised questions about whether the factory can be completed on schedule.

TSL is expected to leave the site within two or three months. At present, no other main build contractor is lined up. NG Bailey, the company handling mechanical, electrical and plumbing work, is thought to be one possible replacement to take on the entire build. Agratas says the site is a large, complex industrial project and that supplier partners are supporting it.

The latest production target is January 2028. The project’s original 2026 start was pushed back to 2027, and the contractor change could add to doubts about the latest date. However, Agratas has not yet delayed its planned start again. The building shell is mostly complete, and National Grid has started work on the required electricity substation.

05

Will the contractor changes stop JLR from selling electric cars, and where could its batteries come from instead?

The contractor changes at Agratas are not expected to stop Jaguar Land Rover selling electric cars. The article says JLR has secured batteries from other suppliers, so its plans to increase sales of new electric Land Rovers and Jaguars will not be affected. That means the immediate concern is where those batteries are made, rather than whether JLR can obtain batteries at all.

The initial cars will not use British-made batteries, because the Somerset factory is not yet producing them. The article does not identify the other suppliers or say where all their batteries will be made. It does say that the manufacturer could avoid EU tariffs under “rules of origin” if it uses batteries made in Europe.

That leaves Agratas’s factory important for a later domestic supply, but its schedule remains uncertain. TSL is leaving, with no replacement main build contractor lined up. Agratas has not yet pushed back its latest planned production start of January 2028, and it says it is on track to meet customer requirements.

06

Why does the UK see domestic battery production as important for its car industry?

The UK sees domestic battery production as important because batteries are key parts of electric vehicles, and global supply is dominated by China, South Korea and Japan. Building a local supply chain could help support the country’s car industry as it moves toward electric vehicles. The government has described the Agratas factory as crucial to the industry’s long-term survival.

The Somerset plant is intended to make batteries for Jaguar Land Rover, Britain’s largest automotive employer, which is Agratas’s sister company in Tata Group. The UK government has pledged £380m toward the £5.2bn project, although not all the support has been paid. At full planned staffing, the factory could employ as many as 4,200 people.

The project has not yet delivered British-made batteries for JLR’s initial electric cars; JLR has secured other suppliers. Contractor departures and schedule delays also leave uncertainty about when local production will begin. Agratas’s latest target is January 2028, and the company says it remains on track to meet customer requirements.

07

Why are EV batteries such a strategic part of car manufacturing, and why is production concentrated in a few countries?

An electric vehicle needs a battery to store electrical energy and deliver it to the vehicle’s electric motor. That makes batteries a central part of making an EV, rather than a minor component. The article calls them important parts of electric vehicles and links secure battery supply to the future of Britain’s car industry. This basic explanation of how batteries power an EV is general knowledge; the article does not detail the engineering.

The article says global battery supply is now dominated by China, South Korea and Japan. It does not explain why production became concentrated in those countries, so the reason cannot be established from this account alone. It does, however, describe the UK’s efforts to build its own battery supply chain, backed by successive Conservative and Labour governments.

Agratas’s Somerset gigafactory is intended to supply JLR and is seen by the UK government as important to the industry’s long-term survival. But contractor departures and delays have left questions about when it will produce batteries. JLR has secured other suppliers for its initial electric cars, which will not use British-made batteries.

This brief was written by AI from the original reporting and checked by other models. Names, figures and quotes come from the source; read it for full context.

Read more in the JupiteX app

Pulse is free. New stories every 4 hours, each one broken into the questions that explain it.

Or read more news on the web